Mixing
Add the dry material to the water and mix with a concrete mixer for around ten minutes. With a power mixer or a drill paddle, around two to three minutes of mixing is sufficient. Allow the plaster to stand for around ten minutes and mix it again for a short while. When using an automatic mixer, ensure that the amount of water does not get too high.
Work instructions
Apply the plaster with a plaster trowel or a pump. A suitable thickness for one layer is 15 mm. If the layer thickness exceeds 20 mm, the work must be done in several layers. Allow the previous layer to dry for one or two days before applying the next layer. In dry conditions, the base must be wetted before applying a new layer of plaster.
Varastointi ja jätteen käsittely
Katso erillinen varastointi ja hävitysohje https://www.fescon.fi/materiaalipankki